Onshore infrastructure and equipment
Features:
- Subsea cable landing point.
- Substation equipped with 2 20 MW 13.2/132 kV of 25 MWA transformers with protection and control panels.
- Electrical installation: from the landing point to the substation (4 x 13.2kV / 5MW), and from there to the power grid (1 x 132kV/20MW).
- Monitoring and control system.
- Research and Data Centre.
Offices for WEC manufacturers with equipment under test, and for personnel of the Centre.
Data monitoring system